Skip Ribbon Commands
Skip to main content

Bridge Name

Schaeffer Road a/k/a Blandon Bridge (53A)

Municipality

Maidencreek Township

Location

Schaeffer Road over the Maiden Creek

Project

​The project will entail the complete replacement of the existing two-span structure with a single span, pre-stressed concrete spread box beam bridge with new abutments and pedestrian sidewalks.  The project is currently under construction, with an completion anticipated in September 2018.

Engineer: Larson Design Group, Inc.
Inspector: McCormick Taylor, Inc.
Contractor: Rylind Construction, Inc. ($1,144,337.92)

Order

01

Attachments

Created at 7/7/2017 9:08 AM by RHunter
Last modified at 7/18/2018 11:02 AM by RHunter