Bridge Name

Hartz Mill Bridge (38A)

Municipality

Caernarvon Township

Location

Mill Road over the Conestoga Creek

Project

The project will entail the replacement of the existing superstructure and deck with select repairs to the abutments and approach roadways. The project is currently completing the public competitive bidding process via PennDOT's ECMS system, with bids due 7/26/2018.​

Engineer: HAKS, under administration by PA Dept. of Transportation, Engineering District 5-0
InspectorPA Dept. of Transportation, Engineering District 5-0

Order

07

Attachments

Created at 7/7/2017 9:28 AM by RHunter