Bridge Name

Zettlemoyer's Bridge (46G)

Municipality

Greenwich Township

Location

Long Lane over the Maiden Creek

Project

The project will entail a limited rehabilitation to the existing steel truss bridge to restore it to a minimum of 10 Ton posted weight limit. The project is completed with design, and is currently in preparation for re-bidding due to no compliant bids being received when originally bid in June 2018 . This project is currently scheduled to be let for bids via the County's Invitation to Bid process in September 2018 with construction commencing in spring 2019.
 
Engineer: McCormick Taylor, Inc.

Order

08

Attachments

Created at 7/7/2017 9:42 AM by RHunter
Last modified at 7/18/2018 1:20 PM by RHunter